Haight’s Creek Irrigation Company

  • 2 – 4 kW turbines (24 kW future) – grid-tie hydroelectric system
  • 120 feet of head
  • 1.6 cfs flow (present)

Gardner Energy designed and installed two four kW “Pelton” wheel impulse turbines with four future turbines proposed. The system takes the excess pressure from an upper reservoir to fill a lower reservoir and produces power and energy used to offset the needs of the irrigation company office. Partial funding for the project was made available through the Federal Bureau of Reclamation.

Read the Case Study View Diagram 1 View Diagram 2